a. A bar AB of diameter 40 mm and 4 m long is rigidly fixed at its ends. A torque of 600 Nm is applied at a section of the bar 1 m from end A. The fixing couples Ta and Tb at the supports A and B are 450N-m and 150 N-m respectively.

b. A propped cantilever of span 'l' carries a uniformly distributed load of 'w' per unit run over its entire span. The value of prop reaction to keep the beam horizontal is 3/8(w.l).

c. A two hinged semi-circular arch of radius 'R' carries a concentrated load 'W' at the crown. The horizontal thrust is w/pi  (pi  =3.14)